The best time to put a spare conduit under a truck depot is when the trench is already open. Once the yard is resurfaced and trucks are back on their normal routes through the site, adding another cable run can mean digging up the same ground and disrupting the operation a second time.
That was the point Mark Lampard, Managing Director of go EV, made during a panel at the EV Infrastructure Summit held earlier this year. The first trucks might only need a handful of chargers, but the underground works could be there for several generations of vehicles.
“It’s so important to look at what they need now, but what you need later,” Lampard said.
What goes in while the trench is open?
While the ground is open, spare conduits can give the fleet a route for additional cabling when more trucks arrive or when the next generation needs higher-powered charging. The time to work out where those conduits should run is while the depot layout is still on the drawing board.
The decision starts with where the next trucks could realistically park and charge. A spare conduit is more useful if it reaches a bay a truck can manoeuvre into without blocking a loading dock or cutting across a busy traffic lane. The same planning applies to space for future electrical equipment and access for the crews that will install it.
Lampard pointed to the Megawatt Charging System (MCS) as an example of how truck charging requirements could change. Designing the entire electrical installation around a future charging system can add substantial cost. Allowing for another cable route while the ground is open gives the operator room to expand as the fleet’s requirements become clearer.
Keep the depot working through construction
Toby Roxburgh, Chair of the National Electric Vehicle Centre of Excellence and moderator of the panel, said staging the work was critical at depots where trucks still need to come and go.
“You can’t afford downtime, so the staging is so important,” Roxburgh said.
That makes construction sequencing an operations decision. If a trench crosses a busy driveway, the depot needs to know when that section can close and how trucks will reach loading bays, parking and dispatch in the meantime. A plan that looks straightforward on a site drawing can become a problem if it takes out the turning area during the morning dispatch window.
Jitesh Singh, Head of Fleet at Waste Management in New Zealand, said the company had used AC charging to get projects started and was looking at DC charging as it brought different vehicles into the fleet. The mix of chargers a depot needs can change as the vehicles and their duties change.
For fleet managers preparing a depot brief, the first trucks determine what needs to work on day one. The next group of trucks helps determine where to leave room. Before the trench is backfilled, it’s worth asking one question: if we need another row of chargers, what will we have to dig up to get power to it?